Government is monitoring the important infrastructure projects in the Jammu division.

In this connection recently Divisional Commissioner Jammu, conducted an extensive tour of Akhnoor and inspected the progress of work on Package I and III of Jammu-Akhnoor Road widening Project.

He took a round of the entire stretch and inspected the work progress on both the packages at several sites including Bhagwati Nagar, Muthi, Domana, Kangrail, Akhnoor and other locations.

The Executive Director NHIDCL apprised the Div Com about the current status of work on the prestigious road project, besides progress achieved so far and the future work plan.

While giving details, he informed that land acquisition has been completed and work on raising piers for flyover under package 1 from 4th Tawi Bridge to Canal Head is in progress.

He directed NHIDCL to expedite the pace of work by increasing men and machinery for timely completion of the work of Package 1.

He instructed GM NHIDCL to ensure that the adjoining road is connected with proper ramps.

He directed the GM NHIDCL to expedite the final works of package 3 and ensure its completion within the set timeline.

It was further informed that over 73 percent work has been completed under package 3 which is of 20.61 KM length from Ganesh Vihar to Khati Chowk and the work on bridges is in progress.